API Pipeline Facility Construction Inspector API-1184 Prüfungsfragen mit Lösungen:
1. Which of the following is NOT covered by API RP 1110?
A) Valves
B) Line pipe
C) Control piping
D) Breakout tanks
2. Which classification reduces the classification within an enclosure from Division 1 to unclassified through adequate positive-pressure ventilation?
A) Type X purging
B) Zone 1 classification
C) Type Y purging
D) Type Z purging
3. Why is communication important when planning a pressure test?
A) To inform the public about the test
B) To keep the test procedure a secret
C) To ensure all parties involved are informed and aware
D) To avoid sharing information with contractors
4. Which types of processes are covered by ANSI Z49.1?
A) Metal fabrication processes only
B) Welding and cutting processes only
C) Soldering and brazing only
D) Welding, cutting, and allied processes
5. What does MOP stand for in API RP 1110?
A) Minimum Overload Pressure
B) Maximum Overload Pressure
C) Maximum Operating Pressure
D) Minimum Operating Pressure
Fragen und Antworten:
| 1. Frage Antwort: D | 2. Frage Antwort: A | 3. Frage Antwort: C | 4. Frage Antwort: D | 5. Frage Antwort: C |