Oracle Project Management Cloud 2021 Implementation Essentials 1Z0-1057-21 Prüfungsfragen mit Lösungen:
1. You have four resources in your organization: P, Q,R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose thebest answer.)
A) S
B) P
C) Q
D) R
2. When implementing Project Performance Reporting, your customer has the following requirements:
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold levelrule is ideal for this kind of KPI definition? (Choose the best answer.)
A) single threshold level range
B) multiple threshold level value
C) single threshold level value
D) multiple threshold levels
3. You havedefined two expenditure types, but they are not available for selection when youenter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
A) The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.
B) The two expenditure types are not assigned to the reference data set that is assigned to theproject unitin which the transaction is performed.
C) The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.
D) The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.
4. Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you setup to meet the customer requirement? (Choose the best answer.)
A) assignment to multiple sets; no common values allowed
B) assignment to one set only; no common values allowed
C) assignment to one set only with common values
D) assignment to multiple sets; common values allowed
5. Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accountingclose cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.
Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)
A) Bell Curve
B) Even
C) Daily Spread Basis
D) S-Curve
E) Back Loaded
Fragen und Antworten:
| 1. Frage Antwort: D | 2. Frage Antwort: C | 3. Frage Antwort: B | 4. Frage Antwort: A | 5. Frage Antwort: C |