PRINCE2 PRINCE2-7-Practitioner Prüfungsthemen:
| Abschnitt | Gewichtung | Ziele |
|---|---|---|
| Thema 1: Integration von Menschen & Projektkontext | 20% | - Nachhaltigkeit, Digitales & Anpassung
|
| Thema 2: PRINCE2-Praktiken | 40% | - Die sieben Praktiken anwenden und anpassen
|
| Thema 3: PRINCE2-Prozesse | 28% | - Die sieben Prozesse anwenden
|
| Thema 4: PRINCE2-Prinzipien | 12% | - Die sieben PRINCE2-Prinzipien im Kontext anwenden
|
PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Prüfungsfragen mit Lösungen
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor's account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in 'managing a stage boundary'?
- A. Progress
- B. Quality
- C. Organization
- D. Plans
Antwort: C 🗳️
Erklärung: (Nur für DeutschPrüfung-Mitglieder sichtbar)
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the 'manage by stages' principle, and why?
- A. Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight
- B. Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions
- C. No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project
- D. No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance
Antwort: D 🗳️
Erklärung: (Nur für DeutschPrüfung-Mitglieder sichtbar)
PLANS
Here are three items of information included in the stage 2 plan.
Under which heading (A-F) should each item be recorded?
Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.
- A. Budget
- B. Products to be delivered
- C. Planning assumptions and prerequisites
- D. Tolerances
- E. Monitoring, control and reporting arrangements
Item 1:
The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.
Item 2:
During stage 2, the project manager will send the project board a summary of design progress every two weeks.
Item 3:
Stage 2 will produce architectural visualizations of the proposed building and its landscaped surroundings. - F. Dependencies
Antwort: B,C,E 🗳️
Erklärung: (Nur für DeutschPrüfung-Mitglieder sichtbar)
Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.
Which role agrees to carry out the work package in the 'managing product delivery' process?
- A. Project support
- B. Senior supplier
- C. Project manager
- D. Team manager
Antwort: D 🗳️
Erklärung: (Nur für DeutschPrüfung-Mitglieder sichtbar)
BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council's operations and facilities teams are ready to receive, operate and maintain the completed centre.
Why is this an appropriate application of the 'confirm project acceptance' activity?
- A. Because all project information should be archived before the completed project product is accepted
- B. Because the project manager should complete the end project performance assessment before any supplier demobilizes
- C. Because the project manager should arrange a celebration before the contractor leaves the site
- D. Because the project manager should confirm that handover to the operational and maintenance environment is complete
Antwort: D 🗳️
Erklärung: (Nur für DeutschPrüfung-Mitglieder sichtbar)
Seite 1 von 12 wird angezeigt.
Fragen 1-5 von 58 werden angezeigt.