SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing C_P2W22_2504 Prüfungsfragen mit Lösungen:
1. When do you use variant bills of material (BOMs)?
A) When a material has multiple BOMs
B) When multiple materials have multiple BOMS
C) When a material has a configurable BOM
D) When multiple materials have similar BOMS
2. Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program.
Which planning strategy do you use?
A) Planning with final assembly (40)
B) Make-to-stock production (10)
C) Assembly processing with production orders (82)
D) Planning without final assembly (50)
3. What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
A) Requirements type
B) Planning strategy
C) Requirements profile
D) Order type
4. What is the focus of repetitive manufacturing?
A) Period and quantity-oriented production
B) Low volume production
C) Production of lot size one
D) Detailed tracking of production orders
5. Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.
A) Automatic goods receipt on confirmation
B) Automatic goods issue on confirmation
C) Automatic print on order creation
D) Default order types
E) Automatic release on order creation
Fragen und Antworten:
| 1. Frage Antwort: D | 2. Frage Antwort: B | 3. Frage Antwort: A,B | 4. Frage Antwort: A | 5. Frage Antwort: A,D,E |