Autodesk Certified Professional in BIM Management for Building Design BIM_MGT_101 Prüfungsfragen mit Lösungen:
1. Which of the following would typically be included in an AECO BIM data handover package at project closeout?
A) 3D views used for clash detection during model coordination.
B) Record models with the required asset data embedded.
C) Federated design models used during clash detection.
D) Internal meeting notes from model coordination sessions.
2. During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.
Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)
A) Create blank sheets for all disciplines.
B) Email PDFs to the contractor every week.
C) Schedule Publishes in Design Collaboration.
D) Update Publish Settings to include sheets.
E) Enable Model Coordination.
3. What is included in a BIM Execution Plan?
A) LOD Matrix and project specifications.
B) Modeling standards and technology ecosystem.
C) Collaboration protocols and project playbook.
D) Project schedule and design playbook.
4. A BIM manager is preparing to share a federated model package with an external cost estimator. The estimator only needs access to quantities and location-based metadata, but not design intent or proprietary elements from other teams.
What is the first step the BIM manager should take to ensure appropriate use and minimize data-related risk?
A) Convert the models into 2D views to avoid exposing embedded metadata.
B) Export the models as PDFs to prevent the third party from modifying geometry.
C) Confirm that the model content, format, and permissions match the recipient's defined scope of use.
D) Verify that the file sizes are small enough for email transmission.
5. The BIM manager is working in an Architectural model that uses the phases Existing and New Construction. They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.
Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?
A) Apply a phase-filter override to the linked model using Visibility/Graphics settings.
B) Map the linked model's phases to the host model's phases in the Revit Link properties.
C) Override the linked view's phase settings using view templates in the host model.
D) Open the linked model and manually change its phase names to match the host model.
Fragen und Antworten:
| 1. Frage Antwort: B | 2. Frage Antwort: C,D | 3. Frage Antwort: B | 4. Frage Antwort: C | 5. Frage Antwort: B |