Oracle Primavera P6 2021 Enterprise Project Portfolio Management 1Z0-129 Prüfungsfragen mit Lösungen:
1. You are a Program Manager reviewing Portfolio Performance dat
a. You see a number of Issues that are assigned to a Responsible Manager. What does Responsible Manager mean within Primavera P6 EPPM?
A) the person who identified the Issue
B) the element from the Organizational Breakdown Structure associated with the Issue
C) the manager to which the Issue has been assigned
D) the person responsible for resolving the Issue
2. You already have a Group created, with a set of users assigned to that Group. You want to add permissions to all of those users. Identify the functionality that you should use to complete this task.
A) Import Permissions
B) Import Groups
C) Modify Users
D) Apply Permissions template
3. Where are tolerances set in Primavera P6 EPPM?
A) in Portfolios
B) in Performance Thresholds
C) in Global Preferences
D) in Performance Status tab
4. Identify the key benefit of Plan Resources View.
A) You can create scenarios using waterline analysis.
B) You can view and analyze resource allocation without assigning resources at the activity level
C) You can identify staffing shortfalls within detailed project plans.
D) You can view and assign resources mapped to appropriate Roles with highest skills.
5. Select the appropriate example that demonstrates how materials are measured in P6.
A) $75/minute
B) $75/Hour
C) $75/day
D) $75/linear foot
Fragen und Antworten:
| 1. Frage Antwort: C | 2. Frage Antwort: A | 3. Frage Antwort: B | 4. Frage Antwort: B | 5. Frage Antwort: C |