Microsoft Project 2010, Managing Projects 070-178 Prüfungsfragen mit Lösungen:
1. All tasks are assigned to multiple team members. A business analyst sends you an e-mail message that contains the dates of her vacation. You need to modify the schedule to reflect delays that are caused only by the business analysts vacation dates. What should you do?
A) Change the working time for the resource calendar of the business analyst.
B) Use the Mark on Track command.
C) Create a new enterprise calendar, and then enter the vacation days.
D) Modify the start and end dates of all the tasks of the business analyst.
2. DRAG DROP You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. (Click the Exhibit button.) Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam's workload? (To answer, drag the appropriate units to the correct locations in the answer area.)
A) 100%, 100%
B) 75%, 100%
C) 100%, 150%
D) 75%, 75%
3. Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A) Change the maximum units for the resource.
B) Assign the resource only to tasks that are scheduled on the working days.
C) Change the working time for the resource.
D) Update the base project calendar.
4. You have a Project 2010 schedule that contains the following tasks: Inactive tasks Manually scheduled tasks Manually scheduled summary tasks Tasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
A) Change all manually scheduled tasks to automatic scheduling.
B) Change all inactive tasks to active tasks.
C) Change all manually scheduled summary tasks to automatic scheduling.
D) Change all tasks that contain strikethrough font to tasks that include normal font.
5. You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010. You need to achieve this goal while maintaining SharePoint synchronization. What should you do?
A) Save the SharePoint task list to a Microsoft Excel file and use the Project Import Wizard.
B) Use the New from SharePoint feature and type the URL that contains the task list.
C) Use the Save to SharePoint feature and type the URL that contains the task list.
D) Open the SharePoint task list in Datasheet view and copy the tasks to a blank project file.
Fragen und Antworten:
| 1. Frage Antwort: A | 2. Frage Antwort: D | 3. Frage Antwort: C | 4. Frage Antwort: B | 5. Frage Antwort: B |